Project Construction Checklist

Groundbreaking: May 2017   Completion: Summer 2019


2017

✔ Contractor offices installed

✔ Project permits completed

✔ Demo of Administration Building completed

✔ Excavation of Aeration Basins begins

✔ Excavation of Aeration Basins completed

✔ First major concrete pour

✔ Anaerobic Digester excavation start

✔ Dewatering Building start construction

2018

✔ Blower/Chemical Building structure complete 

✔ Aeration Basin concrete completed 

✔ Primary Clarifier covers installed

✔ Aeration Basins operational

✔ Demo of existing Aeration Basins

✔ Demo of sludge storage building

2019

✔ Primary Clarifier Odor Control operational 

✔ Dewatering Building operational 

✔ Anaerobic Digester and Support Building operational 

• UV Building operational

• Demo of UV Building 

✔ Secondary Clarifiers  3 and 4 operational

✔ Treatment Complex work completed 

• Headworks operational 

• Demo of existing Headworks 

• Secondary Clarifiers 1 and 2 operational

• Paving 

• Project Complete

View the Construction Checklist (PDF)