Groundbreaking: May 2017 Completion: Summer 2019
2017
✔ Contractor offices installed
✔ Project permits completed
✔ Demo of Administration Building completed
✔ Excavation of Aeration Basins begins
✔ Excavation of Aeration Basins completed
✔ First major concrete pour
✔ Anaerobic Digester excavation start
✔ Dewatering Building start construction
2018
✔ Blower/Chemical Building structure complete
✔ Aeration Basin concrete completed
✔ Primary Clarifier covers installed
✔ Aeration Basins operational
✔ Demo of existing Aeration Basins
✔ Demo of sludge storage building
2019
✔ Primary Clarifier Odor Control operational
✔ Dewatering Building operational
✔ Anaerobic Digester and Support Building operational
• UV Building operational
• Demo of UV Building
✔ Secondary Clarifiers 3 and 4 operational
✔ Treatment Complex work completed
• Headworks operational
• Demo of existing Headworks
• Secondary Clarifiers 1 and 2 operational
• Paving
• Project Complete
View the Construction Checklist (PDF)